The future of St James hall looks a little
brighter!
Over the past year the Hall
Committee, in conjunction with architects, have
produced a three-stage plan for refurbishment, which has been approved by
Gloucester City Council.
The estimated cost of the required
works is just over £240,000 and as our application for a national lottery grant
has unfortunately been turned down, this money will have to be raised by a
combination of our organising fund raising events and applying for other grants
which may be available.
The reality of the hall
situation currently is that with the small funds we have we can only try to get
essential and achievable jobs done in the hope that in the very near future we
will have enough money to complete the more major stages of the refurbishment.
There are several ideas on the table regarding funding for the hall,
including one where the County Council would inject substantial funds towards
the refurbishment in return for rent free use of the hall for their current
requirements such as school meals etc.
The hall is still open for
social event bookings on Saturday and Sunday afternoons and any donations
towards the refurbishment fund would be greatly appreciated.
The Latest Progress on The Hall
In July last year, St James
hall committee decided to give the go a
head to, carry out the bare essential work, to bring the hall up to an
acceptable standard for all the hall users.
The finance of the work will
come from the limited donation we have received and rent from the hall users.
I Please to say, in November
last year The community pay back scheme commenced essential refurbishment
work in St James Community Church hall. The
Guys are doing a good job and by time you read this report they should have
completed the task.
The work was carried out on
the weekend only, hence Monday to Friday use of the hall was not affected.
Other jobs which have been
done recently, a deep clean was carried out in the hall back in October A new flat roof was laid to the rear of the hall. New strip lighting which have been welcome by all.
The flooring in the hall will
be sanded and re-sealed in the next few weeks.
The hall finance is reasonable
healthy.
The feed back I've received from
the hall users up to date have been very encouraging, every one like what they
are seeing. Hopefully when all the work is completed it should make all users
of the hall feel positive about the place.